Consequence of delay · Line 6 has no committed recovery date; the opening remains exposed.
Recommended next step · Escalate the overdue plan to Faisal and seek the consortium’s recovery-date commitment.
Eng. Faisal Al-Otaibi · Steering Committee Q3

11 items need attention
Consequence of delay · Line 6 has no committed recovery date; the opening remains exposed.
Recommended next step · Escalate the overdue plan to Faisal and seek the consortium’s recovery-date commitment.
Eng. Faisal Al-Otaibi · Steering Committee Q3
Consequence of delay · The remaining eastern ring parcels continue to block road works.
Recommended next step · Escalate the three unresolved parcels and agree a dated settlement route.
Eng. Turki Al-Mutairi · Board resolution 9/1448
Consequence of delay · Land and utilities constraints prolong the eastern ring delay.
Recommended next step · Escalate the three outstanding parcels and prioritise utility diversions.
Eng. Turki Al-Mutairi · Programme register · next escalation checkpoint
Consequence of delay · Supplier selection and the façade delivery schedule remain unresolved.
Recommended next step · Return the supplier comparison with cost and lead-time trade-offs.
Dr. Hessa Al-Rashid · Steering Committee Q3
Consequence of delay · Crossing 3 closure planning remains unsupported by an agreed traffic study.
Recommended next step · Complete the study before deciding the November closure arrangement.
Eng. Khalid Al-Dosari · Executive Committee
Consequence of delay · The irrigation award and December mobilisation may slip.
Recommended next step · Obtain the completed evaluation memo and confirm the award route.
Dr. Sara Al-Harbi · Steering Committee Q3
Consequence of delay · Depot commissioning cannot proceed without a confirmed utilities connection schedule.
Recommended next step · Agree the connection sequence and escalate the unresolved utilities dependency.
Eng. Nasser Al-Jaber · Executive Committee
Consequence of delay · Declining productivity and unresolved crossings threaten November works.
Recommended next step · Resolve D3 and agree a recovery sequence across the roads and boulevard teams.
Eng. Khalid Al-Dosari · Programme register · next escalation checkpoint
Consequence of delay · The Board may have to consider recovery without an assured schedule.
Recommended next step · Have Faisal complete the recovery paper and independent schedule assurance for 29 Oct.
Eng. Faisal Al-Otaibi · Board resolution 14/1448
Consequence of delay · The widening schedule gap threatens the Line 6 opening.
Recommended next step · Secure an independently assured recovery schedule for the Board paper.
Eng. Faisal Al-Otaibi · Programme register · next escalation checkpoint
Consequence of delay · Crossing approvals may delay Sports Boulevard works and disrupt November access.
Recommended next step · Resolve D3 and agree the traffic-management plan with the Ministry of Sport.
Eng. Khalid Al-Dosari · Leadership letter 3321