Delivery
Main & Ring Roads Development
Off track
Budget spent 81%
SAR 7.9bn of SAR 9.8bn
Spend · 81%
Schedule 62% vs plan 74% · 12 pts behind plan
Schedule variance · 6 periods
Dashed line: −5 pt early-warning threshold · latest -12 pts
Top risks
- Land acquisition on eastern ring
- Utility diversions
Public sentiment
Ring road congestionEasing
Complaints easing after new interchange.
Prepared by your office · Sources: Public social listening (illustrative) · 24 Oct 2026
Linked directives
Close out eastern ring land acquisitionOverdue
Linked decisions
Reallocate SAR 80m to roads utilities · 19 Oct 2026
Establish a joint utilities coordination office · 14 Oct 2026
Commission eastern ring land valuation review · 13 Oct 2026