Delivery
Sports Boulevard
At risk
Budget spent 55%
SAR 4.7bn of SAR 8.6bn
Spend · 55%
Schedule 47% vs plan 53% · 6 pts behind plan
Schedule variance · 6 periods
Dashed line: −5 pt early-warning threshold · latest -6 pts
At risk · Earthworks productivity declining; variance doubled in two periods.
Top risks
- Earthworks productivity
- Crossing approvals with roads programme
Public sentiment
Road closures near Sports BoulevardRising
Commuter complaints on temporary diversions.
Prepared by your office · Sources: Public social listening (illustrative) · 25 Oct 2026
Linked directives
Align Sports Boulevard crossings with roads programmeAt risk
Linked decisions
Defer Crossing 5 to phase two · 23 Oct 2026