Delivery
Green Riyadh
On track
Budget spent 53%
SAR 5.9bn of SAR 11.2bn
Spend · 53%
Schedule 54% vs plan 55% · 1 pts behind plan
Schedule variance · 6 periods
Dashed line: −5 pt early-warning threshold · latest -1 pts
Top risks
- Irrigation water supply
- Nursery capacity
Public sentiment
Shade and tree cover in summerRising
Positive mentions of new canopy in northern districts.
Prepared by your office · Sources: Public social listening (illustrative) · 25 Oct 2026
Linked directives
Approve Green Riyadh phase three scopeOn track
Linked decisions
Extend nursery contract by 6 months · 21 Oct 2026
Pause northeast parks design pending funding · 16 Oct 2026
Approve irrigation tender shortlist · 15 Oct 2026